  • Berth A (deeper (100 m), further offshore (16 km)); Berth B (shallower (50 m), nearer shore (6 km)

Berth A (deeper (100 m), further offshore (16 km)); Berth B (shallower (50 m), nearer shore (6 km) | Atlantic Marine Energy Test Site (AMETS)

Atlantic Marine Energy Test Site (AMETS)
Atlantic Marine Energy Test Site (AMETS)
Lead Organisation Sustainable Energy Authority of Ireland (SEAI)
Country Ireland
Type Wave
Website http://www.oceanenergyireland.ie/TestFacility/AMETS
  • Type of Testing Wave
    Year Established 2011
    Temperate/Tropical Temperate
    Commercial/Array/Full scale/Scale Full scale, Research (non-commercial)
    Development Status All permissions in place; infrastructure build to commence

    Overview

    The Atlantic Marine Energy Test Site (AMETS) is being developed by Sustainable Energy Authority of Ireland (SEAI) to facilitate testing of full-scale wave energy converters in an open ocean environment.
    AMETS will be located off Annagh Head, west of Belmullet in County Mayo and will be connected to the national grid.
    The test site is an integral component of Ireland’s Ocean Energy Strategy and is being developed in accordance with the national Offshore Renewable Energy Development Plan (OREDP).
    The site will be focused on wave energy and will provide two separate test locations at various depths of water to allow for a range of devices to be tested.
    It is envisaged that the test site will provide a grid connected national test facility, to which full scale wave energy converters could be coupled during their final stages of pre-commercial development.
  • Number of Berths 2
    Water Depth A = 100 m, B = 50 m
    Min Water Depth (m) 50
    Max Water Depth (m) 100
    Avg Water Depth (m)
    Annual mean significant wave height
    Maximum recorded wave height
    Mean (averaged current speed)
    Maximum current speed
    Maximum tidal range
    Mean wind speed
    Max wind speed
    Seabed type A mix of sand, gravel/coarser sediment and bedrock at seabed.
    Total test area (km2) 8.4
    Distance to land 6 - 16 km
    Grid connected Y
    Grid connection capacity 10 MW
    Rated export capacity and connection
    Proximity to nearest harbour (km) The test sites will be accessible via Frenchport Pier; 14 km from Berth A & 6 km from Berth B.
  • Demonstration Projects

    No demonstration project has been deployed yet.

    R&D Projects

    No R&D project has been deployed yet.

    Infrastructure

    The test site is not yet in operation for developers but SEAI can offer interested developers a suite of detailed information such as live met-ocean data measurements, numerical wave modelling reports including wave propagation and wave energy assessments, offshore site investigations including vibrocores and multi-beam surveys.

    Equipment available to support site deployments

    2019/2020 – environmental surveying is ongoing.
    Wave Rider Buoy and ADCP are permanently deployed at Berth A and Berth B. See Data Buoy Dashboards for (nearly) live information.

    Key supply chain companies in the region